Quick take
- Standard Lithium and its partner Equinor, through their joint venture Smackover Lithium, now expect to make a final investment decision on the South West Arkansas project by the end of the first quarter of 2027, with construction beginning shortly after, the company said in its third quarter report Thursday, Nov. 12.
- Financing is the last major step. The partnership is now seeking more than $1.2 billion in senior secured project debt, up from its first target of up to $1.1 billion. The company says the export credit agency process has taken longer than expected, but the due diligence review is substantially complete with no material concerns.
- The other three big requirements are done: construction contracts, federal environmental approval and customer sales agreements. LG Energy Solution and Trafigura have agreed to buy up to 20,000 metric tons a year of lithium carbonate for 10 years.
- The central processing plant is planned about eight miles south of Lewisville. At a community meeting in Lewisville, officials said construction would take about three years, peaking in early 2028 with about 600 workers at the plant and 250 more on wellfield work, the El Dorado News-Times reported.
Standard Lithium said in its third quarter report on Thursday, Nov. 12, that Smackover Lithium, its partnership with Norwegian energy company Equinor, now expects to make a final investment decision on the South West Arkansas lithium project in Lafayette County by the end of the first quarter of 2027, with construction starting shortly after.
Where it stands
The company says three of the four big requirements before that decision are done: contracts with the construction firms, approval under the National Environmental Policy Act, and customer sales agreements. LG Energy Solution and Trafigura have agreed to buy up to 20,000 metric tons a year of battery-quality lithium carbonate for 10 years once production starts.
The last piece is financing. Smackover Lithium is working with export credit agencies from the U.S., Canada and Norway and is now targeting more than $1.2 billion in senior secured project debt, up from its first goal of up to $1.1 billion. "While the ECA financing process has taken longer than initially anticipated, the comprehensive due diligence review is substantially complete without any material concerns," the company said.
The construction contractors have been working under a limited notice to proceed for six months on engineering, ordering long lead equipment, permits and community work, the company said.
What it means locally
The El Dorado News-Times reports the project is a $1.5 billion plant with its central processing facility about eight miles south of Lewisville. It would pull lithium from underground brine in the Smackover Formation, turn it into lithium carbonate for batteries and put the leftover brine back underground. The first phase is designed to make 22,500 metric tons a year.
At an earlier community meeting in Lewisville, company officials said construction would take about three years, with first production targeted for 2029 and commercial operations in 2030, the paper reported. Construction work was expected to peak in early 2028 with about 600 workers at the processing plant and about 250 more on wellfield work.
Standard Lithium will discuss the quarter on a webcast at 4:30 p.m. Eastern (3:30 p.m. CST) Monday, Nov. 16.