Quick take
- Utility regulators in Texas, Louisiana and Arkansas have all approved SWEPCO's Hallsville Natural Gas Plant and found it in the public interest, SWEPCO said, as reported by the Longview News-Journal and KLTV.
- The plant is going up on the site of the former coal-fired H.W. Pirkey Power Plant, off FM 3251 near Brandy Branch Reservoir (Pirkey Lake), KLTV reported.
- SWEPCO says it will have two 225 megawatt units, 450 megawatts in all, enough for about 400,000 homes at peak demand, and can start up in about 11 minutes.
- SWEPCO says the project will bring 250 jobs to Hallsville. The plant is expected to begin serving customers in late 2027.
The old Pirkey power plant site near Hallsville is getting a second life. Utility regulators in Texas, Louisiana and Arkansas have all approved Southwestern Electric Power Co.'s Hallsville Natural Gas Plant, with each one finding the project is in the public interest, SWEPCO said this week, according to the Longview News-Journal and KLTV.
The plant is being built where the coal-fired Henry W. Pirkey Power Plant ran for years, off FM 3251 near Brandy Branch Reservoir, also known as Pirkey Lake. SWEPCO expects it to start serving customers in late 2027.
What SWEPCO says it will do
- Power: two turbines and two generators, each rated at 225 megawatts, for 450 megawatts in all. SWEPCO says that is enough for about 400,000 homes at peak demand.
- Quick start: the company says the plant can go from a dead start to producing power in about 11 minutes, which it pitched as a backup for emergencies and bad weather.
- Jobs: SWEPCO says the project will bring 250 jobs to Hallsville, KLTV reported.
- More than a plant: the site, which SWEPCO calls the Hallsville Energy Hub, also holds the company's Regional Distribution Center, putting generation, operations and logistics in one place.
Community leaders, elected officials and economic development partners toured the site Thursday, Nov. 19, KLTV reported. "It's about economic development. It means new jobs," state Rep. Jay Dean told the station.
SWEPCO serves customers in Texas, Louisiana and Arkansas, which is why all three state commissions had to sign off. The company has not said in these reports what the plant will cost or what, if anything, it will mean for customer bills.